Salzburg, October 30, 2026
During its review of the planned Festival construction in Salzburg, the Court of Auditors identified further cost risks not previously included in the cost planning and put the potential total cost at EUR 636.23 million.
The Court of Auditors criticized the fact that the project management had failed to take several cost components into account in its cost presentation. These include land costs, the costs of interim venues, and additional operating costs of the building project owner organization.
The Festival Fund points out that the additional amounts represent a possible range of variation. Under the relevant and industry-standard rules for cost planning, particularly ÖNORM B 1801-1, this figure is not part of the cost framework.