Rendsburg, 16 July 2026
During the night leading into Thursday, the 118-metre-long, approximately 1,250-tonne middle section of the first half of the bridge was lifted into place at a height of 50 metres during the construction of the new Rader Hochbrücke over the Kiel Canal near Rendsburg.
The steel element had been loaded onto a floating pontoon at the port of Rendsburg the previous day. The pontoon then covered the roughly six-kilometre stretch to the lifting point beneath the bridge. The actual lifting operation using so-called strand jacks began in the evening at around 9:30 p.m., according to a statement from the Federal Waterways and Shipping Administration. For the spectacular lift starting at approximately 9:30 p.m., the constructors need space – which is why shipping traffic is being stopped for 16 hours, from 5 p.m. on Wednesday to 9 a.m. on Thursday.
According to information from Deutsche Einheit Fernstraßenplanungs- und -bau GmbH (DEGES), the middle section was loaded using two Self-Propelled Modular Transporters, whose axles can be coupled as needed. The middle section required 13 axle lines per transporter. „Der Grund, warum wir das nachts machen, ist, dass morgens um 5.00 Uhr das Bauwerk am kühlsten, am kältesten ist und damit die Lücke auch am größten. Denn Stahl und Beton zieht sich bei Kälte zusammen und dehnt sich bei Wärme aus und wir wollen sichern, dass wir oben auch in die Lücke reinpassen“, erläuterte DEGES-Projektleiter Martin Steinkühler.
