Munich, July 22, 2026
Lufthansa and Munich Airport have announced the concrete expansion of Terminal 2, which, with a new building called the "T-Stiel," is to create capacity for up to ten million additional passengers per year.
Background: The "T-Stiel" Project
Munich Airport and Lufthansa presented the expansion plans together. Airport CEO Jost Lammers and Lufthansa hub manager Heiko Reitz explained the project, which is currently in the concrete planning phase. From 2035, the so-called "T-Stiel" is to go into operation, named after the shape of the planned extension, which will be built at a right angle behind the existing Terminal 2.
According to the parties involved, the extension will be 550 meters long and will be financed through the existing joint venture between the airport and Lufthansa. Once completed, the "T-Stiel" is to offer space for twelve wide-body aircraft or 22 smaller planes. A more precise cost calculation is not yet available according to the airport; initial estimates had most recently put the figure at around two billion euros.